Work has started on the bridge abutments, the foundations of the Bridge Foundation work including earth and rock excavation, concrete forming, concrete pouring is expected to take up to 6-8 weeks. The bridge super structure is being built off site, delivery is expected in 16 weeks. Upon arrival the bridge super structure will be put in place on the abutments.