Paul Revere Historic Site

Work has started on the bridge abutments, the foundations of the Bridge Foundation work including earth and rock excavation, concrete forming, concrete pouring is expected to take up to 6-8 weeks. The bridge super structure is being built off site, delivery is expected in 16 weeks.  Upon arrival the bridge super structure will be put in place on the abutments.