On Monday, Murray Paving the reclamation contractor will begin work on Morris Drive and Pleasant Street. The work will consist of lowering the manhole and catch basin frames and covers in preparation for reclaiming the asphalt. Murray Paving anticipates the casting work will take no more than two (2) days to complete. On Tuesday, they will begin the reclamation process on Morris Drive and move onto Pleasant Street. They anticipate the reclaiming and grading to take 4-5 days to complete.
Paving the binder coarse is tentatively scheduled for the week of August 8th and will take approximately two (2) days to complete.
Police and Fire apparatus will have total access to all areas of the work zones.