The Town has been advised of the following anticipated schedule for the completion of the current phase of the Metropolis Rink project:
September 14, 2015 - RebuildEx completes partial demolition
September 17, 2015 - Gale Engineering on-site inspection
September 30, 2015 through October 6, 2015 - Gale conducts analysis of accumulated data
October 15, 2015 - Gale Engineering issues report of findings
October 22, 2015 (estimated) - RebuildEx dollarizes Gale Engineering report
Note: Sometime after September 14, 2015 the insurer's retained mechanical consultant will re-inspect the ice rink's slab due to issues regarding HVAC piping. This schedule is subject to change if unexpected events are encountered.