Streetscape Project
Update
January
9, 2009
Construction Update Report
November 21, 2008
Construction Update Report
October 27, 2008 Construction
Update Report
September 22, 2008 Construction Update
Report
August 25, 2008
Construction Update Report
Town of Canton is announcing the restart of the Downtown
Streetscape Project’s final phase. Startup is scheduled for on
or about April 1. It is expected the project will be
completed on or about September 30th,
The Canton Public Works Department will be
overseeing the Washington Street “sidewalk and street rehabilitation”
project. This work will be ongoing for approximately four weeks along
Washington Street, between Ridge Hill Road and Pecunit Street. Funding
for the project will be provided for by the State under the Chapter 90
roads program. Please
see Streetscape Project tab below, for more important contact
information including; specifically assigned staff available
to assist the public with any questions and or issues that may
come up.
Please note:
in order to accomplish the completion of all work, traffic
will be impacted in the Downtown. As a result, all motorists
are asked to be aware of this work and to expect delays. The
Town of Canton appreciates the cooperation and patience of
everyone, especially the businesses located in downtown
Canton.
Board of Selectmen – Announce Opening
Streetscape Project –
Oversight and Management Office
Location: 719 Washington Street (Rear - first
floor behind The Newsstand)
In order to provide downtown businesses and
resident’s access to knowledgeable streetscape project personnel and
information, the Board of Selectmen has required the opening of this
office.
Located
conveniently in the downtown, the office is staffed with project
representatives available to the public as a resource for information
relating to the project, including any complaints, issues or
questions.
Inquires
may be made in person or via telephone by calling 781-575-0550.
Project
Representatives available to assist include:
1. Waterfield Representative – Jeff Kane
2. Town of Canton - Town Engineer – Jim Donovan, 781-821-5063,
jdonovan@town.canton.ma.us
Design Plan
(PDF - 11 MB)
July 5, 2007
RE: Downtown Streetscape Project – Update
Dear Owner/Operator,
As you may know the Downtown Streetscape
Project construction will begin on or about July 16, 2007. The Town
has engaged J. Marchese & Sons Inc. of Everett MA for this project.
The first phase of the work will begin in the
area of Neponset Street and Cape Cod Lane. The public should be
aware this phase of work will last approximately seven weeks.
The entire project is “contracted” to be
completed by May 2008.
The Project will be supervised by the Public
Works Department (Engineering Division), Waterfield Design (our
design consultant) and a specifically assigned Clerk of the Works
also representing the Town and property owners and operators located
in the Downtown. Our Clerk will be charged with making sure the
project is built as designed and to assist with any problems or
issues that present themselves along the way.
The Town requests anyone with any problems or
concerns regarding the project contact our Clerk. To make this
communication more efficient, the Clerk and the Contractor will rent
space in the Downtown area. They will hold office hours and regular
meetings concerning project progress and deal with any issues that
need to be addressed. At the appropriate time, contact information
will be widely distributed including direct telephone line access to
key project representatives.
In the initial start up phase if you need to
make contact for any reason please call Mr. James Donovan, Canton
Town Engineer. Jim will be the Project Director. He can be reached
by calling (781) - 821-5063.
A copy of this letter will also be sent to the
Downtown Business Association and the Canton Association of
Industries. Please share this information with anyone you feel would
have an interest.
Please consult Canton Cable Eight and the Town
Web Site for more information as it becomes available.
June 7, 2007 - Board of Selectmen Announce
Construction Start Date
Board of Selectmen has successfully petitioned the State for
supplemental funding and has received notification that the Town will
receive an additional $847,000 for this important Downtown project.
Total project grant funding now totals 2.66 million dollars.
The construction phase of the Project will begin
on or about July 15th, 2007.
The Board of Selectmen has made final changes to
project design to minimize impact on downtown parking in response to
feedback received during the design phase. The Board continues to
finalize administrative matters related to the project, including
contract execution, as the bidding process has already been completed.
The contractor is set to mobilize in the downtown on or about July
15th. Informational mailings, web notices, media stories and
additional public meetings are planned.
Streetscape improvements are designed along the
route in public areas on Washington Street, from Sherman to Neponset
Street. Improvements include; brick and concrete sidewalks, new
granite crosswalks, historic style traffic lights, planting areas and
public shade trees, new signage, benches and a variety of landscaped
pocket parks to name a few examples.
A portion of the grant funding will be used to
hire a full time project manager to be responsive to business and
residential concerns that may present themselves during the
approximately seven month construction schedule.
Additional details and information to follow.
Downtown Streetscape Project
Design Planning Committee
Mission Statement
It shall be the duty of the
Downtown Streetscape Project Design
Planning Committee (DSPDPC) to guide and oversee, on behalf of the
Board of Selectmen, the public communication and outreach process to
ensure the public plays an active and effective roll in determining
the ultimate streetscape improvements to be accomplished in the
downtown. The Committee is charged with establishing
innovative, convenient and efficient communication methods to ensure
public participation throughout the design process. The
Committee shall oversee the identification and recommend the
selection of the most qualified design firm based on experience with
similar projects. The Committee shall also identify a
reasonable and efficient schedule for the completion of the design
portion of this project. The Committee shall organize and
utilize various public outreach methods including conducting a
series of public meetings. Such outreach shall be designed to
make the public aware of the project goals, progress, elicit
information and feedback as to the kinds of streetscape improvements
the general public, residents of the downtown, business owners and
property owners, feel will best accomplish the overall goals of a
Downtown Revitalization effort consistent with the State grant.
the Committees work shall be complete upon the approval of the final
design of the streetscape improvements by the Board of Selectmen.
Further, the Committee shall be responsible, from time to time on an
as needed or as directed bases, to provide to the Board of
Selectmen, status reports as to the progress of the committees
activities.
Committee Members
|
Shirley Morse - Beautification Comm |
Christina Carlton - Staff |
|
Christopher Podgurski - Citizen |
Charles E. Doody - Fire Dept |
|
James Donovan - Town Engineer |
Ed Walsh - Building Commissioner |
|
Helena Findlen - Police Dept |
Helen McHowell - Downtown Business |
|
Judith Nelson - Staff |
Kevin McCormick - Downtown Business |
|
Lisa Lopez - Citizen |
Mike Trotta - Supt. of Public Works |
|
Avril Elkort - Selectmen |
Sal Salvatori - Selectmen |
| .Recreation |
William T. Friel - Town Administrator |
|
Planning |
|
Tentative Meeting Schedule
All meetings are open to the public and held on Wednesday at 8:00 am in the Salah
Meeting Room, Memorial Hall, 801 Washington St, Canton MA unless otherwise noted:
December 15
|
December 29
|
January 5 *
|
January 12
|
January 20 *
|
January 26 - cancelled
|
February 9
|
February 22 *
|
February 23
|
March 1 *
|
* January 5, Wednesday at 7:00 pm with DBA and CAI at Library
Community Room
* January 20, Thursday at 7:00 pm - Open to the Public at Library
Community Room
* February 22, Tuesday evening to present rough draft report to
Board of Selectmen
at Town Hall in the Salah Meeting Room (time to
be announced)
* March 1, Tuesday evening to present final report and presentation to
Board of Selectmen
at Town Hall in the Salah Meeting Room (time to
be announced)
Current Meeting Agenda
(pdf)
Project Documentation
Grant Submission Form
Letter of Award
RFP for Design Services
(pdf 845K)
(pdf 45K)
(pdf 1.3MB)
Design Concepts
Public involvement is crucial to the design and
implementation of the Downtown Streetscape Project. As such we
have compiled some examples of different projects that have been
completed.
Design Concept
Examples
(Powerpoint show 4MB)
Constituent Feedback
If you have any
comments or suggestions you can click on the link below and submit
your ideas to the committee.
On-Line
Questionnaire
|